The two numbers you need
For crumb rubber infill, two published figures do most of the work:
- New installs: 2 to 3 lb per square foot. The New York State Department of Health's fact sheet on crumb-rubber infilled fields says crumb rubber "is typically applied at a rate of two to three pounds per square foot of field surface."
- Top-ups: about 0.55 lb per square foot per ¼-inch lift. In SportsTurf (October 2012), field maintenance contractor Jim Cornelius wrote that "most crumb rubber infill calculates to 0.55 pounds per square foot for a ¼-inch lift."
Everything else is multiplication. Your system manufacturer's spec overrides both, because infill depth and the rubber/sand split vary by system.
What size infill?
NYSDOH describes turf crumb pellets "ranging from about one-sixteenth to one quarter inch in diameter." In sieve terms:
- 1/16 inch ≈ 1.6 mm
- 1/4 inch ≈ 6.4 mm
That's why the common turf grades are 10-20 mesh (passes 2.00 mm, mostly held on 850 µm) and 8-16 mesh (passes 2.36 mm, mostly held on 1.18 mm). Your system spec will name one or the other, or a blend.

New field math
Football field (with end zones)
360 ft × 160 ft = 57,600 sq ft
| Rate | Pounds | Supersacks (~2,000 lb) | Truckloads (~42,000 lb) |
|---|---|---|---|
| 2.0 lb/sq ft | 115,200 | ~58 | ~3 |
| 2.5 lb/sq ft | 144,000 | ~72 | ~3.5 |
| 3.0 lb/sq ft | 172,800 | ~87 | ~4 |
Add the run-offs
Most installed fields extend past the playing lines. If the carpet area is 80,000 sq ft:
- 80,000 × 2 = 160,000 lb to 80,000 × 3 = 240,000 lb
- 80 to 120 supersacks, 4 to 6 truckloads
Measure the carpet area, not just the lines.
A rubber/sand system
Many systems put down sand first for ballast, then rubber. If your system calls for, say, 1.5 lb/sq ft of rubber over sand on 80,000 sq ft:
- 80,000 × 1.5 = 120,000 lb of rubber, about 60 supersacks, 3 trucks
Use your system's actual rubber rate. We only supply the rubber.
Top-up math
Infill doesn't stay put. Cornelius's article lists the usual suspects: infill is "carried off by players, wind, rain, snow, snow removal, routine maintenance." He recommends measuring infill depth at multiple points (his crew uses 10 locations, following ASTM's Gmax test-point layout) and adding material where it's low. On a field with 2¼-inch fibers, he flags fields with less than 1½ to 1¾ inches of infill as needing more.
Annual top-up for one field
High-wear zones (goal mouths, center, sidelines) total 25,000 sq ft and need a ¼-inch lift:
- 25,000 × 0.55 = 13,750 lb, about 7 supersacks
A district with five fields
- 5 × 13,750 = 68,750 lb, about 34 sacks, under 2 truckloads
- One delivery to a central yard, then distribute: freight per pound drops sharply versus five small shipments
Infill for a new field or a season of top-ups? Get it priced. Send grade, volume, delivery city/ZIP and your target price.
Request a QuotePlanning deliveries
- Site access. Can a 53-ft trailer get in? Is there a forklift on site, or do you need a liftgate or a contractor's telehandler?
- Staging. Supersacks need a dry, flat staging area near the field. Cover them.
- Timing. Infill goes in after the carpet is laid and seamed. Schedule deliveries for that window, not weeks early.
- Count and check. Count sacks against the bill of lading. Note any torn or wet sacks before the driver leaves.
What the research says
Buyers, boards and parents ask about safety. Here's what two primary sources actually say:
- EPA/CDC/CPSC Federal Research Action Plan (FRAP). In July 2019, EPA released Part 1 – Tire Crumb Characterization. The research collected tire crumb from synthetic turf fields (280 microbial samples came from 40 fields). EPA's summary says the findings "support the premise that while chemicals are present as expected in the tire crumb rubber, human exposure appears to be limited based on what is released into air or simulated biological fluids." EPA is also clear that the report "is not a risk assessment."
- NYSDOH fact sheet. Reviews heat, injury, infection, latex allergy and chemical exposure. It states that "results from numerous studies suggest that the potential for chemical exposures from crumb rubber in synthetic turf is low," notes that analyses in California and Washington State have not found support for cancer associations with turf field use, and flags heat as a real consideration. In a BYU measurement NYSDOH cites, average synthetic turf surface temperature was 117°F versus 78°F for natural grass.
We're a material supplier. Field owners, system manufacturers and local health authorities make the policy calls. We just make sure the rubber you buy matches the spec you were given.
What to put in a turf infill PO
- Grade: 10-20 or 8-16 (or the system's named gradation), tested by ASTM D5644
- Residual steel and fiber limits
- Moisture and dust/fines limits
- Total pounds with a ± tolerance
- Delivery: site address, unloading equipment, delivery window
- Paperwork: lot sieve report with each load
Common mistakes
- Ordering by field lines instead of carpet area. Run-offs add a lot of square feet.
- Mixing grades mid-install. Stick to one grade per field unless the system calls for a blend.
- Storing sacks uncovered. Wet infill clumps and spreads unevenly.
- Skipping the top-up budget. Infill loss is normal. Plan for it.
Measuring infill depth the practical way
Top-up math only works if you know where infill is low. The method Cornelius describes is simple and repeatable:
- Pick fixed test points. His crew uses 10 locations laid out like ASTM's Gmax test points, so the same spots are measured every time.
- Measure depth from the top of the infill to the backing, or measure exposed fiber above the infill, using a depth gauge or a simple probe.
- Record each point with the date. Over a few seasons, you'll see which zones lose infill fastest.
- Compare to the system spec. Your turf manufacturer specifies the target depth for the fiber height you have.
- Top up low zones first, then groom to redistribute.
High-traffic areas such as goal mouths, the center of the field and team areas on the sidelines usually lose infill faster than the corners. Snow removal can strip infill from wide areas in a single storm, so check depth after winter.
Getting the math right on odd-shaped fields
Not every field is a rectangle. Baseball and softball fields, practice areas and multi-use fields need a little geometry:
- Break the area into rectangles and triangles, calculate each and add them up.
- Use the as-built drawing from the turf installer if you have it. It usually lists total turf area.
- Subtract areas without infill, such as inlaid pads or areas with a different system.
Example: a practice field plus a warm-up strip
Main area 220 ft × 120 ft = 26,400 sq ft. Warm-up strip 120 ft × 20 ft = 2,400 sq ft. Total 28,800 sq ft.
At 2.5 lb/sq ft: 28,800 × 2.5 = 72,000 lb, about 36 supersacks, under 2 truckloads.
Budgeting for the life of the field
Infill isn't a one-time purchase. A realistic budget includes the initial fill, yearly top-ups, and replacement material when the carpet is replaced or the infill is cleaned and reused. Talk to your system manufacturer about whether the infill can be recovered and reused at carpet replacement. Planning a few sacks a year for each field is far easier than finding an emergency budget when a goal mouth is worn down to the backing in mid-season.
One more tip: buy top-up rubber that matches
When you top up a field, use the same grade the field was built with, or the grade your system manufacturer approves for maintenance. Mixing a much finer or much coarser grade into an existing field changes how the infill packs and drains, and it can make the surface play differently in the topped-up zones. Ask your installer what went into the field, and keep that information with your maintenance records.
Frequently asked questions
How many pounds of crumb rubber per square foot of turf?
About 2 to 3 lb per sq ft for new installs (NYSDOH), and roughly 0.55 lb per sq ft per ¼-inch top-up (Cornelius, SportsTurf).
How many tons of infill does a football field take?
A 57,600 sq ft field at 2-3 lb/sq ft takes about 58 to 86 tons of crumb rubber. Fields with run-offs take more.
What mesh is turf infill?
10-20 and 8-16 are common; NYSDOH describes turf crumb as about 1/16 to 1/4 inch.
Can you deliver straight to the field?
Yes. We quote delivered freight to your site.
How often do fields need top-ups?
Cornelius's article recommends measuring infill depth and replacing what's lost, typically annually.
Sources: NYSDOH, Information About Crumb-Rubber Infilled Synthetic Turf Athletic Fields (health.ny.gov); J. Cornelius, "The basics of maintaining synthetic turf," SportsTurf, Oct. 2012 (archived PDF); U.S. EPA, July 2019 Report: Tire Crumb Rubber Characterization (epa.gov).